Study of Irrigation Project In View of Cost and Time Overruns

Authors

  • Shripad A. Bhagat  TSSM's Padmabhooshan Vasantdada Patil Institute of Technology Pune, Maharashtra/India. Savitribai Phule Pune University, Maharashtra, India
  • Prof. Nikhil V. Bhalerao  TSSM's Padmabhooshan Vasantdada Patil Institute of Technology Pune, Maharashtra/India. Savitribai Phule Pune University, Maharashtra, India

Keywords:

Land Acquisition; Rehabilitation; Cost Overruns; Price Fluctuations

Abstract

It is well known that most irrigation projects in India exposed to time and cost overrun or both. This phenomenon may affect the progress of country as well as may expose many institutions of construction to be destroyed. The aim of this paper is to study of irrigation projects in view of cost and time overruns of irrigation projects in Amravati region. The study clarified that “Land acquisition, Rehabilitation affected people and Increase in CSR rate was the most critical factor that influences project delay. The survey also indicated that "Other reasons" occupied the second rank in importance, where "Changes in Structural Design, Establishment tools and plant (ETP) and Extra work" were among the most important factors affecting delay. The study illustrated that "prices fluctuations of constructions project due to other reasons" which was changes in design, land acquisition, Delay in government approval, oppose of farmers and unforeseen ground conditions these are the most important factors that may lead to cost overrun. Also it clarified that contractor's delay of material delivery and equipment have led to cost overrun. The study also clarified that prices inflation highly contributes to cost overrun. The study recommended government, contractors, and consultants to hold their responsibilities to avoid any delay or cost overrun which could be achieved by good management of the project and finding new methods for storing the needed materials from the beginning of the project.

References

  1. Ogunlana Stephen and promkuntong K., and Jearkjirm, V, “Construction delays in a fast-growing economy: comparing Thailand with other economics”, International Journal of Project Management, Vol.14, No.1. (1996)
  2. Pablo Gonozalez, Vicente Gonzalez, “Analysis of Causes of Delay and Time performance in Construction Projects”. Journal of Construction Engineering and Management. (2013)
  3. Abderisak Adam, Per-Erik Josephson and Göran Lindahl, “Implicationof cost Overruns and Time Delays on Major public Construction Projects”,(2010).
  4. Vijay Perincherry and Fang Wu, “Cost of Project Delays: An Estimate of Foregone Benefits and Other Cost Related to Schedule Delays of Inland Waterway Projects”. Decision Economics, (2012).
  5. Jomah Mohammed Al-Najjar , “Factors Influencing Time and Cost Overruns on Construction Projects in the Gaza Strip.”  The Islamic University of Gaza April, (2008).
  6. Al- Khalil M. and AL-Ghafly M., “Delay in public utility projects in Saudi Arabi”. International Journal of Project Management, Vol.17, No.2, pp.101-106 ,1999.
  7. Tommy Y. Lo, Ivan W. H. Fung, and Karen C. F. Tung, “Construction Delays in Hong Kong Civil Engineering Projects”,Journal of Construction Engineering and Management Vol,132,No.6 (2006 ).
  8. Jasper Kranker Larsen, Geoffrey Qipping Shen, “Factor Affecting Schedule Delay, Cost Overrun,and Quality Level in Public Construction Projects”, Journal of Management in Engineering (2016).
  9. Andrew Shing-Tao Chang, “Reasons for Cost and Schedule Increase for Engineering Design Projects”, Journal of Management in Engineering, Vol18,No.1 ,(2002).
  10. Aibinu A.A and Jagboro G.O., “The effects of construction delays on project delivery in Nigerian construction industry”, International Journal of Project Management, Vol. 20, No. 8, pp. 593-599, (2002).

Downloads

Published

2017-06-30

Issue

Section

Research Articles

How to Cite

[1]
Shripad A. Bhagat, Prof. Nikhil V. Bhalerao, " Study of Irrigation Project In View of Cost and Time Overruns, IInternational Journal of Scientific Research in Computer Science, Engineering and Information Technology(IJSRCSEIT), ISSN : 2456-3307, Volume 2, Issue 3, pp.840-843, May-June-2017.